Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You are planning to conduct the team-building portion of your new project management training curriculum out-of-doors in the local park. You are limited to scheduling the course at certain times of the year, and the best time for the course to begin is mid-July. You are using the precedence diagramming method for your schedule. In it, you can show relationships between tasks in four ways, and the most common is-
A
Finish-to-start
B
Finish-to-finish
C
Start-to-start
D
Start-to-finish
Explanation: 