Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
At various points during project execution, the project manager reviews the project charter. Which of the following best describes what a project charter may be used for when the work is being completed?
|
To make sure all the team members are rewarded
|
|
To help determine if a scope change should be approved
|
|
To assess the effectiveness of the change control system
|
|
To make sure that all the documentation on the project is completed
|
Explanation:
Detailed explanation-1: -Expert judgment is a tool and technique used to develop the project charter.
Detailed explanation-2: -The project charter typically documents the following parts of the project: Project objectives and constraints. Key stakeholders. Risks identified.