You are working on a project to remodel a home, and you and your team decided you should first finish the plumbing work and then do the electrical work. In this example, this is an example of a-
A
Start-to-finish approach
B
Discretionary dependency
C
Mandatory dependency
D
Finish-to-start approach
Explanation: 

Detailed explanation-1: -Planning The plan established during this process helps project managers oversee scope, cost, timelines, risk, quality issues, and communications. It is during this phase that project managers will outline key deliverables and milestones and identify the tasks that must be completed to complete each.

Detailed explanation-2: -Create a project plan. Develop a resource plan. Define goals and performance measures. Communicate roles and responsibilities to team members. Build out workflows. Anticipate risks and create contingency plans.