You have a project with the following activities Activity A t.1kes 40 hours and can start after the project starts. Activity B takes 25 hours and should happen .1ftcr the pro1cct starts. Activity C must happen C after activity A .md t.1kcs 35 hours. Activity D must happen after activities Band C and takes 30 hours. Activity E must take place after activity C and takes I 0 hours. Activity F takes place after Activity E and takes 22 hours. Activities F and D are the last activities of the project. Which of the following is true if activity B actually takes 37 hours?
A
The critical path is 67 hours.
B
The critical path changes to Start, B, D, End
C
The critical path b Start, A, C, E, F, End.
D
The critical path increases by l 2 hours.
Explanation: 

Detailed explanation-1: -Some activities that might be involved include: Mailing invitations. Booking the venue. Hiring a caterer.

Detailed explanation-2: -Project initiation is the first step in starting a new project. During the project initiation phase, you establish why you’re doing the project and what business value it will deliver-then use that information to secure buy-in from key stakeholders.

Detailed explanation-3: -Create a project plan. Develop a resource plan. Define goals and performance measures. Communicate roles and responsibilities to team members. Build out workflows. Anticipate risks and create contingency plans.

There is 1 question to complete.