Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You can use various estimating approaches to determine activity durations. When you have a limited amount of information available about your project, especially when in the early phases, the best approach to use is-
A
Bottom-up estimating
B
Analogous estimating
C
Reserve analysis
D
Parametric analysis
Explanation: 

Detailed explanation-1: -Parametric Estimating As an important tool to estimate activity duration, the Parametric Estimation Technique can be considered as a consolidation of historical information and statical data.

Detailed explanation-2: -Project estimation is the process of forecasting the time, cost, and resources needed to deliver a project. It typically happens during project initiation and/or planning and takes the project’s scope, deadlines, and potential risks into account.