Your lead engineer estimates that a work package will most likely require 50 weeks to complete. It could be completed in 40 weeks if all goes well, but it could take 180 weeks in the worst case. What is the expected duration of the work package?
A
45 weeks
B
70 weeks
C
90 weeks
D
140 weeks
Explanation: 

Detailed explanation-1: -The most likely duration is an estimate of the most probable duration of a particular activity. This type of duration takes into the account all the known variables that may affect the performance of the entire project.