Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Your project schedule was approved. Management has now mandated that the project be completed as soon as possible. However, you do not think it is possible given resource constraints. In order to convince your management of your need for additional resources, you decide to use-
A
Resource manipulation
B
Resource breakdown structure
C
Critical chain scheduling
D
Resource leveling
Explanation: 

Detailed explanation-1: -Sequence Activities-The process of identifying and documenting relationships among the project activities. Estimate Activity Durations-The process of estimating the number of work periods needed to complete individual activities with estimated resources.

Detailed explanation-2: -Step 1: Create a Work Breakdown Structure (WBS) A Work Breakdown Structure (WBS) is used for estimating the project scope by breaking it down into easily manageable components, or bites. WBS is the hierarchical list of project’s phases, tasks, and milestones.