Basis in developing the concept of QMS in ISO 9001 is according to which concept?
A
PDCA
B
TPPA
C
CPPA
D
COPPA
Explanation: 

Detailed explanation-1: -The ISO 9001:2008 Standard is based on the PDCA (Deming ) Cycle often referred to as the ‘cycle of continual improvement’.

Detailed explanation-2: -The Plan Do Check Act (PDCA) cycle is a management method. Also known as the Deming cycle, or the Shewhart cycle, it involves 4 steps: Plan what you are doing.

Detailed explanation-3: -management system. Performance can be managed and improved by applying the Plan-Do-Check-Act. (PDCA) cycle. This applies equally to the system as a whole, to individual processes and to operational activities.