A control chart shows seven data points in a row on one side of the mean. What should be done?
A
Perform a design of experiments
B
Adjust the chart to reflect the new mean
C
Find an assignable cause
D
Nothing. This is the rule of seven and can be ignored
Explanation: 

Detailed explanation-1: -Statistical Process Control (SPC) is a collection of statistical techniques aimed at identifying assignable causes of variations in a process by monitoring the process and analysing the data obtained.

Detailed explanation-2: -Trend – Seven or more consecutive points are increasing or decreasing. A basic rule of thumb is when a run chart exhibits seven or eight points successively up or down, then a trend is clearly present in the data and needs process improvement.