Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
A control chart shows seven data points in a row on one side of the mean. What should be done?
|
Perform a design of experiments
|
|
Adjust the chart to reflect the new mean
|
|
Find an assignable cause
|
|
Nothing. This is the rule of seven and can be ignored
|
Explanation:
Detailed explanation-1: -Statistical Process Control (SPC) is a collection of statistical techniques aimed at identifying assignable causes of variations in a process by monitoring the process and analysing the data obtained.
Detailed explanation-2: -Trend – Seven or more consecutive points are increasing or decreasing. A basic rule of thumb is when a run chart exhibits seven or eight points successively up or down, then a trend is clearly present in the data and needs process improvement.