Benchmarking involves comparing actual or planned project practices to those of comparable projects with all of the following characteristics EXCEPT:
|
To identify best practices and generate ideas for improvement.
|
|
To provide a basis for measuring performance
|
|
Within the performing organization or outside of it.
|
|
Within the same application area but not in a different application area.
|
Explanation:
Detailed explanation-1: -the elements of benchmarking consist of 8 elements as follow: 1) team/staffs 2) bench marking’s title 3) com-parative companies 4) benchmarking indicators 5) data collection method 6) analysis data and results 7) report of results 8) action plan development.
Detailed explanation-2: -The process of benchmarking involves identifying key metrics, assessing where you currently are, determining where you want to be and creating an action plan to achieve and measure your goals.