In quality management, you plan to conduct tests for objective information about the product or service under test according to project requirements. Your intent in conducting these tests is to is:
|
Ensure the product is acceptable under certain circumstances
|
|
Examine the work products to see if they conform to requirements
|
|
Take action to bring a defective or nonconforming component into compliance
|
|
Find errors, defects, bugs, or other non-conformance problems
|
Explanation:
Detailed explanation-1: -Quality control in project management. Quality control involves operational techniques meant to ensure quality standards. This includes identifying, analyzing, and correcting problems. While quality assurance occurs before a problem is identified, quality control is reactionary.
Detailed explanation-2: -Major deliverables to be tested. General standards & criteria. Monitoring and controlling activities. Quality control schedule.