SOFTWARE PROJECT MANAGEMENT
QUALITY MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Processes often interact with one another. For example, the output of a process may be an input to another process in a different knowledge area. An example from quality management is:
|
Verified deliverables
|
|
Realized benefits
|
|
Business value
|
|
Process metrics
|
Explanation:
Detailed explanation-1: -Validated changes and validated deliverables are the outputs of the quality assurance process. Controlling quality involves monitoring specific project results to ensure that they comply with the relevant quality standards while identifying ways to improve overall quality.
Detailed explanation-2: -The four main stages of project quality management are quality planning, quality control, quality assurance, and quality improvement.
There is 1 question to complete.