ISO 9001:2015 has introduced the concept of risk based thinking in quality management.
A
true
B
false
C
Either A or B
D
None of the above
Explanation: 

Detailed explanation-1: -Risk-based thinking has always been in ISO 9001 – this revision builds it into the whole management system. In ISO 9001:2015 risk-based thinking needs to be considered from the beginning and throughout the system, making preventive action inherent to planning, operation, analysis and evaluation activities.

Detailed explanation-2: -One of the key changes in the 2015 revision of ISO 9001 is the establishment of a systematic approach to risk. Rather than treating it as a stand-alone component of a QMS, the updated ‘sum of the parts’ approach sees it no longer separated from the whole.

Detailed explanation-3: -According to ISO 9001, planning for risk is a form of quality management and doing so contextually ensures that the business’ quality management system is able to achieve its intended results by preventing or reducing the risk and also mitigating any of the potential side effects of an undesired outcome.