The ____ is used to identify what might go wrong in a plan under development.
|
Pareto Chart
|
|
PDPC
|
|
Arrow Diagram
|
|
Matrix Diagram
|
Explanation:
Detailed explanation-1: -The process decision program chart (PDPC) is defined as a new management planning tool that systematically identifies what might go wrong in a plan under development. Countermeasures are developed to prevent or offset those problems.