Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
true
|
|
false
|
|
Either A or B
|
|
None of the above
|
Detailed explanation-1: -A quality manual is no longer specifically required. The new standard requires the organization to maintain documented information necessary for the effectiveness of the quality management system (QMS).
Detailed explanation-2: -Responsibilities of the management representative. As mentioned above, a management representative is not mandatory according ISO 9001:2015, but because those activities are still required, this role can still be very valuable in the implementation and maintenance of the Quality Management System.
Detailed explanation-3: -The ISO 9001 standard requires, through clause 7, that your organisation provides adequate resources to operate an effective Quality Management System. This includes providing resources for: Robust infrastructure. Efficient working environments.
Detailed explanation-4: -List policies to be written (note any ISO requirements that do not apply). Draft policies based on applicable ISO requirements. List operating procedures or refer to them as appropriate. More items •15-Nov-2018