The first six sigma methodology is DMAIC, which consists of DMAIC:Define, Measure, Analyze, Improve, Control
|
True
|
|
False
|
|
Either A or B
|
|
None of the above
|
Explanation:
Detailed explanation-1: -’Define’ is critical to Six Sigma’s success. As its name suggests, Define is about describing the problem and setting the goal. During this stage, the team identifies the high-level focus and leadership required to carry the project out.