Which of the following is not a limitation of total quality management?
|
Training and Development Funds
|
|
Competitive Advantage
|
|
Bureaucratic
|
|
Only works if there’s commitment
|
Explanation:
Detailed explanation-1: -Reduced costs and better cost management. Higher profitability. Improved customer focus and satisfaction. Increased customer loyalty and retention.
Detailed explanation-2: -Which of the following is not a characteristic of Total Quality Management? Explanation: TQM focuses on customer needs, continuous improvements, and quality circles. Waste reduction is a quality of lean manufacturing, not TQM.