Which of the following is NOT a tool for Quality Planning?
|
Pareto Diagram
|
|
Benchmarking
|
|
Experiment Designing
|
|
Cost-Benefit Analysis
|
Explanation:
Detailed explanation-1: -Quality planning often uses various tools which form an integral part of the entire quality management plan. Often the most common tool is benchmarking, a process of comparing a project with other similar projects. Other tools include flow charts, check sheets and cause and effect diagrams.
Detailed explanation-2: -In other words, to ensure quality, you must meet the needs of the stakeholder. Meeting or exceeding requirements, however, is not part of project quality management.