SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 10 of 100Question ID:612459A project manager is in the process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness.Which of the following is least likely to be updated as a result of this process?
A
AThe issue log
B
BTest and evaluation documents
C
CThe risk register
D
DThe lessons learned register
Explanation: 

Detailed explanation-1: -Much like a project within a project, the risk identification life cycle is a process that delivers key elements of an overall risk management plan. The Risk Identification process itself follows a defined structure and is elaborated progressively through six stages: Template specification. Basic identification.

Detailed explanation-2: -"Monitor Risks is the process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project."

Detailed explanation-3: -Create a project risk register. Identify project risks. Identify opportunities. Determine likelihood and impact. Determine the response. Estimation. Assign owners. Regularly review project risks. More items