SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 74 of 100Question ID:612001You and the project management team have been vigilant about observing different aspects of the project to ensure the project is progressing as planned. Currently, you are using performance data generated during project execution to determine if the status of overall project risk has changed, if the project assumptions are still valid, if contingency reserves for cost or schedule require modification, and if project strategy remains valid.What process are you performing?
A
APlan Risk Responses
B
BMonitor Risks
C
CPlan Risk Management
D
DIdentify Risks
Explanation: 

Detailed explanation-1: -The fourth project management phase, project monitoring and control, takes place concurrently with the execution phase of the project. It involves monitoring the progress and performance of the project to ensure it stays on schedule and within budget.

Detailed explanation-2: -What should be done by the project manager to ensure that all work in the project is included? Register now or log in to answer. The correct answer is (C) Create a WBS.

Detailed explanation-3: -Time management processes provide the mechanism to decompose work into small, manageable chunks.

There is 1 question to complete.