Question 21 of 100Question ID:612009Your company was awarded a contract that includes a 10% bonus payment if the project is completed two months early. You consider several options to exploit this opportunity.What is the best course of action for you to increase the chances of receiving the bonus?
|
AReduce project scope
|
|
BLevel resources
|
|
CCrash the schedule
|
|
DPurchase insurance
|
Explanation:
There is 1 question to complete.