SOFTWARE PROJECT MANAGEMENT
RISK MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Question 25 of 100Question ID:612321A software development team implemented pair programming as a risk response. In a subsequent risk review, it was determined to be highly effective in catching programming errors and dramatically reducing the number of escaped defects.As a result of the risk review meeting, what should the project manager do first?
|
ASubmit a change request to update the risk management plan
|
|
BNotify the project management office (PMO) of results from the risk review meeting
|
|
CCapture the information in the lessons learned register
|
|
DUpdate the lessons learned repository with the knowledge gained
|
Explanation:
Detailed explanation-1: -The Risk Manager provides an overview of the project’s risks and opportunities as well as their mitigation plan (for risks) or exploitation (for opportunities) facilitating management’s decision-making. They are the central figure for the project’s risk management activities.
Detailed explanation-2: -11) Which of the following best describes the executive summary in the risk management plan? Ans: Introduction to the conditions of the project and an outline of the potential risks.