Question 8 of 100Question ID:612705As your project progresses and creates product increments with each consecutive iteration, the project team carries out the Collect Requirements process and Identify Risks process to collect new requirements and identify new risks. You want to ensure that work planned for the upcoming iterations is completed with the consideration of the new risks and requirements.What is your best course of action?
A
AReprioritize work in a risk-adjusted backlog
B
BHold an iteration retrospective meeting
C
CUpdate the requirements-risk repository
D
DDistribute a risk report after each iteration
Explanation: 

Detailed explanation-1: -Risk management involves identifying what risk categories are most likely to affect your project and making a plan to mitigate those risks. Project management tools make risk management easier because they allow you to organize your projects from start to finish.

Detailed explanation-2: -The purpose of a risk register in project management is to record the details of all risks that have been identified along with their analysis and plans for how those risks will be treated. Basically, it’s a log that identifies risks along with their severity and the actions and steps to be taken to mitigate the risk.