Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 27 of 100Question ID:612444A key team member has left the project, and the planned risk response is implemented by replacing the team member with an individual that is very capable and highly productive. However, the project manager now feels there is a risk that the productivity of the team may suffer as a result of not having an established working relationship with the replacement team member.This new risk is an example of which type of risk?
A
AResidual risk
B
BRisk enhancement
C
CSecondary risk
D
DReserve risk
Explanation: 

Detailed explanation-1: -Risk response strategies: mitigation, transfer, avoidance, acceptance.

Detailed explanation-2: -Project managers should work to eliminate the threats before they occur. Similarly, the project managers should work to ensure that opportunities occur. Likewise, the project manager is also responsible to decrease the probability and impact of threats and increase the probability and impact of opportunities.

Detailed explanation-3: -Mitigate. This risk response strategy helps you lessen the impact or probability of the risk. This strategy decreases the severity. For example, a team member may leave during the peak of your project.