Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Question 42 of 100Question ID:612239An agile software development project consists of four releases, with features incrementally added with each release. Due to an excessive number of defects found by users after the first release, the risk response plan was implemented, which involved more rigorous testing by the project team. After the second release, the client has reported two bugs.What must first be done to determine the effectiveness of the implemented risk response?
|
ASchedule a release retrospective
|
|
BComplete a sensitivity analysis
|
|
CConduct technical performance analysis
|
|
DPerform a reserve analysis
|
Explanation:
Detailed explanation-1: -On which of the following is Agile Software Development based? Agile Software Development based on both incremental and iterative development.
Detailed explanation-2: -Four values of Agile individuals and interactions over processes and tools; working software over comprehensive documentation; customer collaboration over contract negotiation; and. responding to change over following a plan.