SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 3 of 100Question ID:613768A project is chartered to install an IT data center in a foreign country where the political climate is highly unstable. To address the threat to the data center due to the political instability, the project manager has negotiated with the U.S. State Department to establish the data center in a high-security basement of the U.S. Consulate.This is an example of:
A
ARisk transfer
B
BRisk avoidance
C
CRisk mitigation
D
DRisk acceptance
Explanation: 

Detailed explanation-1: -The PRINCE2 Directing a Project process starts when the Starting Up a Project process completes and is triggered by the request from the project manager to initiate a project. The PRINCE2 project board uses the technique management by exception.

Detailed explanation-2: -Minimum requirements You must have at least two management stages. You must produce and maintain a project plan, a stage plan for each management stage and exception plans when requested. You must use product-based planning when creating all plans.

Detailed explanation-3: -It is used to provide a full and firm foundation for Initiating a Project and is created in the Starting up a Project process by the Project Manager. The Project Brief is then used in the Initiating a Project process and extended into the Project Initiation Documentation .

There is 1 question to complete.