Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 92 of 100Question ID:613797During a risk review meeting for project nearing completion, a new risk has been identified. This risk may affect the project’s schedule.What should the project manager do first?
A
AMitigate the risk
B
BAlert the project sponsor of the potential impact
C
CImplement the fallback plan
D
DAnalyze the risk
Explanation: 

Detailed explanation-1: -After the potential risks have been identified, the project team then evaluates each risk based on the probability that a risk event will occur and the potential loss associated with it.

Detailed explanation-2: -Create a risk management plan. Keep your risk register up to date. Understand the risk event. Be proactive instead of reactive. Develop your project management skills. 25-Mar-2020

Detailed explanation-3: -Decide on your process. Get to know your stakeholders. Choose your risk management toolkit. Start risk identification. Coach for risk action planning. Begin a second round of risk identification. Run a second risk review board. Encourage reflection. More items •29-Nov-2021