Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Question 92 of 100Question ID:613797During a risk review meeting for project nearing completion, a new risk has been identified. This risk may affect the project’s schedule.What should the project manager do first?
|
AMitigate the risk
|
|
BAlert the project sponsor of the potential impact
|
|
CImplement the fallback plan
|
|
DAnalyze the risk
|
Explanation:
Detailed explanation-1: -After the potential risks have been identified, the project team then evaluates each risk based on the probability that a risk event will occur and the potential loss associated with it.
Detailed explanation-2: -Create a risk management plan. Keep your risk register up to date. Understand the risk event. Be proactive instead of reactive. Develop your project management skills. 25-Mar-2020
Detailed explanation-3: -Decide on your process. Get to know your stakeholders. Choose your risk management toolkit. Start risk identification. Coach for risk action planning. Begin a second round of risk identification. Run a second risk review board. Encourage reflection. More items •29-Nov-2021