SOFTWARE PROJECT MANAGEMENT
RISK MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
APerform the Conduct Procurements process
|
|
BUpdate the risk register
|
|
CImplement the agreed-upon risk response
|
|
DSubmit a change request to update the cost baseline
|
Detailed explanation-1: -Ideally, you should create your risk management plan during the project planning phase. That way, you can best identify any risks and their potential impact and monitor those risks during the project.
Detailed explanation-2: -The PMBOK® Guide describes risk as, An uncertain event or condition, that if it occurs, has a positive or negative effect on a project’s objective. The key element of this definition is that the effect of the uncertainty, if it occurs, may be positive or negative on the objectives of the planned endeavour.
Detailed explanation-3: -Risk Management Process. Managing risks on projects is a process that includes risk assessment and a mitigation strategy for those risks. Risk assessment includes both the identification of potential risk and the evaluation of the potential impact of the risk.