Question 29 of 100Question ID:651336The project keeps running into similar errors. The project manager is surprised, as she had plans in place to mitigate these errors.What is most likely the root cause of these errors?
A
AIncompetent project team members
B
BRisk response plan not being implemented
C
CNot enough meetings are held
D
DHaving repeating errors is normal for any project
Explanation: 

Detailed explanation-1: -Project crashing in project management is a method used to speed up a project’s timeline by adding additional resources without changing the scope of the project.

Detailed explanation-2: -Adopt the Proactive Approach. Plan Project’s Strategy and Project’s Implementation. Manage the Project Goals. Avoid Unrealistic Expectations. Track Project’s Progress. Identify Risk Factors. Propose the Solutions. Use Correct Methodology. More items •23-Feb-2018

Detailed explanation-3: -Plan Diligently. As a project manager, look at the bigger picture. Identify Loopholes. Check Your Resources. Set Realistic Expectations. Track Project Progress. Communicate Well, Communicate Often. Use The Correct Methodology.