Question 44 of 100Question ID:612320A project produces pistons and connecting rods with extremely tight tolerances. The first few pistons were scrapped, as they were not within the limits specified by the contract. The identified risk response was the acquisition of equipment that could machine pistons more precisely.With the new equipment in place, what should be done next to determine the effectiveness of the risk response?
A
AMake a test run to gather work performance information
B
BPerform technical performance analysis
C
CProduce a test batch to gather work performance data
D
DProduce all of the pistons required by the contract and then scrap any that fall outside the specification limits