Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 51 of 100Question ID:612363The computer system is hit with a denial-of-service attack for the second time during a project, and the development team is unable to continue working. The project manager immediately reviews the recorded risk response plans and provides the risk owner with an update about this recurring issue.What else should the project manager do in this scenario?
A
AExamine the risk register
B
BCheck the lessons learned matrix
C
CReview the risk management plan
D
DResearch the lessons learned register
Explanation: 

Detailed explanation-1: -The select stage involves choosing the controls that will be used to protect affected systems to minimize or mitigate the risks that have been identified.

Detailed explanation-2: -Financial Risks: Financial risks involve a project’s monetary factors. Strategic Risks: Strategic risks involve the strategies chosen to complete a project. Performance Risks: Performance risks involve the overall project performance. More items •23-Jun-2022