SOFTWARE PROJECT MANAGEMENT
RISK MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
AUse the results; the simulation data can still be of value because incorrect estimates are accounted for in the algorithm
|
|
BReject the results and use the triangular distribution technique instead
|
|
CUse the results but set aside additional contingency reserves to address the project risks
|
|
DReject the results; the Monte Carlo results would be inaccurate and should not be used34
|
Detailed explanation-1: -Project managers and decision-makers use the Monte Carlo Simulation tool to estimate the impacts of various risks on the project cost and project timeline. Using this method, one can easily find out what will happen to the project schedule and cost in case any risk occurs.
Detailed explanation-2: -The Monte Carlo simulation is a mathematical technique that predicts possible outcomes of an uncertain event. Computer programs use this method to analyze past data and predict a range of future outcomes based on a choice of action.
Detailed explanation-3: -Identify the Transfer Equation. The first step in doing a Monte Carlo simulation is to determine the transfer equation. Define the Input Parameters. Set up the Simulation in Engage or Workspace. Simulate and Analyze Process Output. 23-Apr-2020