Question 9 of 100Question ID:612091A current project is much larger in size and complexity compared to the previous projects that the project manager has managed. To save time and effort, the project manager uses the risk management plan and risk register from a historical project as a template. During project execution, several unexpected high-impact risks were realized, which derailed the project and caused its termination before completion.What most likely caused the project to be terminated?
A
AUsing templates to create the risk management plan and risk register
B
BFailing to implement the agreed-upon risk responses
C
CLack of tailoring of the risk management plan and risk register
D
DPropinquity was too high during project planning
Explanation: 

Detailed explanation-1: -A risk register is a tool in risk management and project management. It is used to identify potential risks in a project or an organization, sometimes to fulfill regulatory compliance but mostly to stay on top of potential issues that can derail intended outcomes.

Detailed explanation-2: -There is a positive correlation between the complexity of a project and the risk. Increased levels of complexity imply more people, newer technologies, and increased internal and external unknown factors.