Question 52 of 100Question ID:612738Your project to build a sports arena near a coastal city is well underway to being completed ahead of schedule this year. Suddenly, a long-dormant volcano erupts nearby, destroying your arena site. The ashfall and the potential for coastal winds to remobilize ash render your site and all on-site assets unusable for two years, exceeding your risk threshold and all contingency and management reserves.What overall project risk strategy should you use?
|
AExploit:Embrace the opportunity to keep your employees on payroll and help the city recover.
|
|
BMitigate:For every seismic warning that an earthquake is imminent, physically cover the site.
|
|
CAvoid:Since you cannot remove the threats, recommend the termination of the project.
|
|
DIncrease:Request the increase of the management reserves allocated for the project.
|
Explanation: