SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 41 of 100Question ID:612241During a project, the project manager introduces a new column to the risk register. This modification proves to be beneficial in monitoring project risks. The project manager documents the best practice in the lessons learned register and plans to transfer this information to the lessons learned repository.What else might the project manager do to ensure this best practice is considered for future projects?
A
AAdd a note to the best practices log for future reference
B
BRecord the information in the issue log
C
CSubmit a change request to update the risk management plan
D
DUpdate the organizational process assets
Explanation: 

Detailed explanation-1: -A risk register is a document that is used as a risk management tool to identify potential setbacks within a project. This process aims to collectively identify, analyze, and solve risks before they become problems.

Detailed explanation-2: -Identify Risks Early With a Risk Register One way to do this is with a risk register. A risk register (also known as a risk log) is an important part of risk management. It’s created at the start project and acts as a tool that helps project managers track issues and deal with them as they arise.

Detailed explanation-3: -Identify risks. Describe risks. Estimate the likelihood and impact of risks. Create a risk response plan. Prioritize risks. Assign risk owners. 20-May-2022

There is 1 question to complete.