Question 63 of 100Question ID:612124In planning a project, a project manager wants to prepare a detailed list of individual project risks and identify potential risk responses along with likely risk owners.What should the project manager do?
A
ACreate the risk register
B
BDevelop the risk assignments report
C
CConduct the Perform Quantitative Risk Analysis process
D
DConduct the Perform Qualitative Risk Analysis process
Explanation: 

Detailed explanation-1: -Identify the risk. Assess the risk. Treat the risk. Monitor and Report on the risk. 27-Sept-2021

Detailed explanation-2: -Identify risks. The first step to getting a grasp on potential risks is to know what they are. Analyze potential risk impact. Assign priority to risks. Mitigate risks. Monitor risks. 17-Jan-2023