SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 7 of 100Question ID:612370A project manager is in the execution stage of a construction project. Poor weather conditions that have hampered progress on the project caused the project to fall behind schedule. Additionally, two of the vendors have been unable to perform as contracted. The project manager now needs to implement the responses planned for these risks.What tool or technique will be most valuable to the project manager in this scenario?
A
AInfluencing to encourage risk owners to take necessary action
B
BFacilitation to improve the effectiveness of risk responses
C
CReserve analysis to determine if the remaining reserve is adequate to implement the risk responses
D
DProbability and impact matrix to assess the odds that the risk responses will be successful
Explanation: 
There is 1 question to complete.