Question 71 of 100Question ID:613611Due to cold weather conditions, it takes more time for the team to complete an activity. The project manager ensures that the response planned for this identified risk is implemented by fast-tracking another activity.What should the project manager do next?
A
ASubmit a change request
B
BUpdate the schedule using the project management information system
C
CConduct a risk audit
D
DPerform risk probability and impact assessment
Explanation: 

Detailed explanation-1: -19. During which risk management process is a determination to transfer a risk made? Transference is a Risk Response Strategy.

Detailed explanation-2: -Come up with alternative solutions and path forward just in case the risk happens. Going through alternative solutions while planning makes it easier for the team to adapt to the change because its already been communicated.

Detailed explanation-3: -The project manager shifts to an agile approach for a project with an aggressive go-to-market timeline. The project manager needs to revise the stakeholder plan so that it follows agile principles.