SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 84 of 100Question ID:613761Your team has just finished identifying potential project risks and is now scheduled to conduct a risk workshop to begin categorizing and prioritizing those risks and assigning risk owners. You decide to bring in a skilled facilitator to help lead the discussion. To enhance the effectiveness of the workshop, the facilitator asks you to bring a few key project documents to the meeting.Which of the following documents would be the least useful to bring?
A
AMilestone list
B
BAssumption log
C
CRisk register
D
DStakeholder register
Explanation: 

Detailed explanation-1: -Performance risk occurs when the project doesn’t perform as well as initially expected. While you can’t always identify the root cause of low performance, you can identify project risks that may lead to low performance and look for ways to prevent those risks.

Detailed explanation-2: -Technical risks. External risks. Organizational risks. Project management risks. 18-May-2022

There is 1 question to complete.