SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 75 of 100Question ID:612197A project team is testing a prototype of a new drone. Something goes wrong and causes the drone to crash and explode. Fortunately, this risk has been identified early in the project, and the contingency reserves allocated for the risk are sufficient to construct another prototype.What should the project manager do next?
A
ASubmit a change request to update the cost baseline
B
BUse the contingency reserves to construct a new prototype
C
CSubmit a change request to tap into the contingency reserves
D
DTerminate the project since the only prototype was destroyed
Explanation: 
There is 1 question to complete.