Question 76 of 100Question ID:612326A vendor went out of business before delivering a component for your project. As a result, the previously planned risk response was implemented by contracting with a different vendor. However, the new vendor will not be able to deliver the component in time to meet the deadline even with the use of the contingency reserves.What should you do next?
A
ATerminate the project
B
BSubmit a change request
C
CFile a claim against the original vendor
D
DPerform the Conduct Procurements process
Explanation: 

Detailed explanation-1: -The document in which the risks are recorded is known as the “risk register” and it is the main output of a risk identification exercise.

Detailed explanation-2: -After you performed Qualitative Risk Analysis you need to create: A prioritized list of risks. List of risks for additional analysis and investigation. List of urgent risks.