Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 78 of 100Question ID:612209A project aims to provide each sales associate with a tablet to use for sales and other transactions. During a trial to test the functionality of the system, the team discovers that the Wi-Fi coverage is inadequate in certain parts of the store.What should be done first?
A
ADiscuss the problem in the next status review meeting
B
BAssess the financial implications of the problem
C
CSubmit a change request to update the schedule baseline
D
DUpdate the project documents
Explanation: 