Which of the following is an output of the Perform Qualitative Risk Analysis process?
A
Project Scope Statement
B
Project Management Plan Updates
C
Stakeholder Register
D
Project Documents Updates
Explanation: 

Detailed explanation-1: -The outputs of the process are updates to the project documents, specifically: the assumptions log. the issue log. the risk register.

Detailed explanation-2: -Qualitative risk analysis uses subjective judgment to determine the probability of a risk occurring and its impact on an organization. The outcome of this process is a list of risks with their corresponding probabilities and impacts.

Detailed explanation-3: -Explanation. An inventory of risk is the output of a risk assessment.

Detailed explanation-4: -A risk register is a document that contains the results of qualitative and quantitative risk analyses and risk response planning.