SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 85 of 100Question ID:613751As part of the planning process, the project manager conducts a meeting with some of the key stakeholders. The purpose of the meeting is to identify the risks associated with the new project. The meeting is highly productive with all members making valuable contributions. At the conclusion of the meeting, a list of risks and potential risk owners has been identified.Where should the project manager capture this information?
A
ARACI chart
B
BRequirements traceability matrix
C
CRisk register
D
DRisk assessment log
Explanation: 

Detailed explanation-1: -Control Communications-The process of monitoring and controlling communications throughout the entire project life cycle to ensure the information needs of the project stakeholders are met.

Detailed explanation-2: -Collect Feedback. Gather, prioritize, and close the loop on product feedback. Engage Customers. Make your customers an invaluable extension of your product team. Inform Product Strategy. Conduct Product Research. Align Internally. Integrations.

There is 1 question to complete.