SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 70 of 100Question ID:612240A project manager has taken over a project early in its execution. The company has a policy that specifies the minimum frequency for conducting risk audits on all projects.What should the project manager do to determine the timing of the risk audits for this particular project?
A
ALook in the project management plan
B
BCheck the applicable policy in the organizational process assets
C
CReview the risk register for risk audit information
D
DUse discretion to determine when and if a risk audit is needed
Explanation: 

Detailed explanation-1: -According to the PMBOK: “Managing project scope is primarily concerned with defining and controlling what is and is not included in the project.”

Detailed explanation-2: -Essentially, the goal of risk management is to identify potential problems before they occur and have a plan for addressing them. Risk management looks at internal and external risks that could negatively impact an organization.

Detailed explanation-3: -Through qualitative and quantitative risk analysis, you can determine how the risk is going to impact your schedule and budget. Project management software helps you analyze risk by monitoring your project. ProjectManager takes that one step further with real-time dashboards that display live data.

There is 1 question to complete.