Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
ASubmit a change request to update the procurement management plan
|
|
BInform all affected stakeholders of the situation and the response plan
|
|
COrder extra parts to store in the warehouse in case the machine breaks again
|
|
DDocument the knowledge gained in the lessons learned register
|
Detailed explanation-1: -When is Risk Breakdown Structure Created PMP. Create your RBS chart during the Project Risk Identification process. Since it is never too early to start thinking about project risks, this process should occur in the project’s early stages.
Detailed explanation-2: -Essentially, the goal of risk management is to identify potential problems before they occur and have a plan for addressing them. Risk management looks at internal and external risks that could negatively impact an organization.
Detailed explanation-3: -Risk Register. The fundamental risk management tool is the risk register. Root Cause Analysis. The root cause is another way to say the essence of something. SWOT. Risk Assessment Template for IT. Probability and Impact Matrix. Risk Data Quality Assessment. Brainstorming. 07-Jul-2022