Question 89 of 100Question ID:651407Midway into project execution, a competitor is about to release a product similar to the one planned to be delivered by your project. If the competitor launches their product to the market before you, your project will be deemed as failed.With a response prepared to run some of the development activities in parallel, what should you do next?
A
ACompress the schedule
B
BMeet with the team to assess the risk
C
CTerminate the project
D
DRequest management reserves
Explanation: 

Detailed explanation-1: -A risk register is a crucial project management tool to document project risks. It’s a document that lists all the potential risks that could occur during the project execution phase, as well as critical information about them.