SOFTWARE PROJECT MANAGEMENT
RISK MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
The Perform Qualitative Risk Analysis process has five inputs, including Risk Register, Risk Management Plan, Organizational Process Assets, and Enterprise Environmental Factors. Which of the following inputs is missing from the list?
|
Teaming Agreements
|
|
Scope Baseline
|
|
Requirements Traceability Matrix
|
|
Resource Calendars
|
Explanation:
Detailed explanation-1: -The inputs to “Perform Qualitative Risk Analysis” are: risk register, risk management plan, project scope statement, and organizational process assets.
Detailed explanation-2: -Explanation. The following are inputs into the process “Perform Quantitative Risk Analysis": risk register, risk management plan, cost management plan, schedule management plan, and organizational process assets.
Detailed explanation-3: -Risk Identification. Risk Analysis. Response Planning. Risk Mitigation. Risk Monitoring. 15-Mar-2021
There is 1 question to complete.