SOFTWARE PROJECT MANAGEMENT
RISK MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Work Performance Reports
|
|
Project Management Plan
|
|
Project Scope Statement
|
|
Work Performance Data
|
Detailed explanation-1: -Probability and impact matrix is not used as an input to the Monitor Risks process.
Detailed explanation-2: -The correct answer is (d) eliminating all risks. Risks cannot be completely eliminated. However, they can be mitigated. The four stages of risk management are identifying risks, assessing them, controlling them, and reviewing the policies.
Detailed explanation-3: -Which of the following is not considered as a risk in project management? Explanation: Testing is a part of project, thus it can’t be categorized as risk.
Detailed explanation-4: -Project risks can be eliminated if the project is carefully planned. All of the following statements about project risks are true EXCEPT: The project manager must ensure that changes to scope do not occur due to risk events.