SOFTWARE PROJECT MANAGEMENT
RISK MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Which of the following is an input to the Identity Risks process?
|
Seller Proposals
|
|
Activity Resource Requirements
|
|
Schedule Management Plan
|
|
Work Performance Information
|
Explanation:
Detailed explanation-1: -A risk management plan documents the whole process, including identification, evaluation, and risk mitigation. It also includes risk control monitoring, cost-benefit analysis, and financial impacts.
Detailed explanation-2: -12. All of the following are ALWAYS inputs to the risk management process EXCEPT: Historical information.
There is 1 question to complete.