SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is an input to the Identity Risks process?
A
Seller Proposals
B
Activity Resource Requirements
C
Schedule Management Plan
D
Work Performance Information
Explanation: 

Detailed explanation-1: -A risk management plan documents the whole process, including identification, evaluation, and risk mitigation. It also includes risk control monitoring, cost-benefit analysis, and financial impacts.

Detailed explanation-2: -12. All of the following are ALWAYS inputs to the risk management process EXCEPT: Historical information.

There is 1 question to complete.